A transmission line from Matiari to Lahore which will be able to transmit 4,000 megawatts of electricity is 85% complete.
The update was given by CPEC Authority Chairperson Lt General (retd) Asim Saleem Bajwa in a tweet on Saturday. This transmission line is of 660 kilovolts.
It will be completed at an overall cost of $1.66 billion. Bajwa said the project will provide direct employment to 2,212 people.
This transmission line is set to evacuate power from North-South and resolve major power-related issues.